I’m pleased to confirm that the planning application for the Wray Crescent Community Park Building was approved on 23rd July at the planning committee meeting. See Decision Notice attached.
The current timeline for the project is as follows:
- Aug-Oct 2024 RIBA Stage 4 – Detailed Design
- Oct-Dec 2024 LBI Procurement Strategy Approval
- Jan-Feb 2025 Tender Process
- Mar-Apr 2025 LBI Contract Award Approval
- May-Nov 2025 RIBA Stage 5 – Construction
We have also launched the consultation on Let’s Talk Islington to hear your suggestions on how the wider park could be improved. Please fill in the survey by Monday 9 September 2024.
Wray Crescent Open Space | Let's Talk Islington